HomeFrontPageAshanti, Western Regions Power Disruptions: GRIDCo blames chainsaw operators for transmission line...

Ashanti, Western Regions Power Disruptions: GRIDCo blames chainsaw operators for transmission line damage

Date:

Related stories

The Ghana Grid Company Limited (GRIDCo) has attributed disruptions to electricity supply in parts of the Western and Ashanti regions to damage sustained by a major transmission line following the felling of a tree by chainsaw operators.

The incident involved the 330kV transmission line connecting Aboadze to Anwomaso, which tripped in the late afternoon of Wednesday, November 25, 2026, resulting in an interruption to power supply.

According to GRIDCo, preliminary investigations conducted by its engineers, including patrols along the affected section of the line, established that a large tree had been felled by chainsaw operators and had fallen onto the transmission infrastructure, causing damage.

In a press statement issued on Wednesday, November 25, the company said the damaged line had affected power transmission to parts of the Western and Ashanti regions.

The outage has particularly affected electricity distribution in parts of Kumasi, where system operators have been compelled to reduce power supply because of the unavailability of the transmission line.

GRIDCo described the affected infrastructure as a critical component of its transmission network and said its engineers were working to repair the damage and restore the line to service.

“Engineers are working diligently to undertake the necessary repairs and restore the affected transmission line as quickly as possible,” the company said.

The power transmission utility apologised to affected consumers for the inconvenience caused by the disruption and assured the public that electricity supply would return to normal once the necessary repairs had been completed.

The incident highlights the potential consequences of unauthorised tree felling and other activities around high-voltage transmission infrastructure, which can compromise electricity supply and damage critical national assets.

However, GRIDCo did not provide details about the precise location of the damaged section, the extent of the damage, the number of consumers affected or a projected timeline for completing the repair works.

The company reiterated its commitment to resolving the situation and restoring normal power transmission as soon as possible.

By 1960news.com

Subscribe

- Never miss a story with notifications

- Gain full access to our premium content

- Browse free from up to 5 devices at once

Latest stories

DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of 1960news.com